Metsi Group’s plants in Ukraine and Estonia offer versatile, cost-effective surface-treated steel structures for several different industries across Europe. The automated beam welding line enables the production of beams up to 21 meters long. The production facilities of Metsi’s Ukrainian plant comprise 22,000 square meters and its annual production capacity for steel structures is 18,000 tons. The Ukrainian plant focuses on heavy steel structures and machine and equipment manufacturing structures. Up-to-date certificates enable us to manufacture bridge elements in addition to steel structures.

The Ukrainian plant is equipped with the most modern production equipment, which is supplied by the world’s leading machine manufacturers (ESAB, Peddinghaus, MG, Promotech, Sci Teex, GEKA, JZ-40, Kemppi Oy, etc.). Many of our production devices are automated, which makes the production of very heavy steel structures possible, including e.g., load-bearing truss structures of bridges.

Certificates: EN ISO 3834-2-2005
                       EN 1090-2 EXC3 – Class B
                       ISO 9001:2015
                       ISO 14001:2015

Max. dimensions of structures:
Beams: 2500 x 800 x 21000 mm
Height of the production facilities 11.7 meters Crane height 8.2 meters
Lifting capacity 30 tons
Painting room: 4500 x 5000 x 33000 mm (width, height, length)

In addition to other welded steel structures, we produce e.g.
the following bars: WQ, HSQ, H, SBSS
and the following profiles: MKC, NSC

References

Steel frames
– 120 tons of steel structures
– year of completion 2019

Fig. 1. Manufacture of steel frames for the mechanical charging system of a blast furnace and for aluminium production for the equipment construction industry.

Steel structures
– 240 tons of steel structures
– year of completion 2020

Fig. 2 Steel structures for a multi-purpose building.

Steel structures
– 233 tons of steel structures
– year of completion 2019

Fig. 3 Steel structures for an administration and storage building, where spare parts for agricultural machinery are stored.

Pontoon
– 15 tons of pontoons
– year of completion 2020

Fig. 4 Manufacture and testing of pontoons.

Drum body blank production
– 330 tons of steel structures
– year of completion 2019

Fig. 5 Drum steel structure.

Production of technological equipment
– 140 tons of steel structures
– year of completion 2017

Fig. 6 Steel structures for technical production equipment.

Steel structures
– 388 tons of steel structures
– year of completion 2019

Fig. 7 Steel structures for light transparent structures.

Pedestrian bridge over the light railway line
– 317 tons of bridge and steel structures
– year of completion 2019–20

Fig. 8a and 8b. Manufacture and installation of steel structures for bridge structures and for lift towers.

Foundation and steel beams
– 140 tons of steel structures
– year of completion 2017

Fig. 9 Manufacture and installation of steel beams and foundation plates for a chocolate factory.

Steel structures for cruise seaport
– 195 tons of steel structures
– year of completion 2016

Fig. 10 Manufacture of steel structures for cruise port.

Production and installation of metal structures
– 250 tons of steel structures
– year of completion
2015–2016

Fig. 11 Manufacture and installation of steel structures.

Mining and processing plant
– 880 tons of steel structures
– year of completion 2012–2013

Fig. 12 Manufacture and installation of steel structures of an ore mining and production plant.

Soda Plant
– 324 tons of steel structures
– year of completion 2011–2012

Fig. 13 Manufacture and installation of steel structures of sodium carbonate plant.

Steel structures
– 218 tons of steel structures
– year of completion 2013–2014

Fig. 14 Manufacture of steel structures for oil industry.

Cement plant
– 8472 tons of steel structures
– year of completion 2008–2011

Fig. 15 Manufacture and installation of steel structures for cement plant.